West Windsor-Plainsboro High School South - Addition & Renovations

WEST WINDSOR-PLAINSBORO REGIONAL SCHOOL DISTRICT

Princeton Junction, New Jersey

The warm weather has sped up progress at West Windsor-Plainsboro High School South. The additions and renovations to the nearly 50 year old building is well underway. Exterior masonry wall construction is nearly complete at the two-story science classroom addition. Exterior brick work will be commencing shortly.

 The concrete slab is poured at the one-story main entrance addition and masons are preparing to start exterior masonry wall construction.

Inside the existing building, renovations at the media center, playhouse theater, culinary lab, and counseling/C.S.T. offices are only a few short months from completion. With many inspections already passed, wall finishes are quickly being installed and the spaces are beginning to take shape.

As part of West Windsor-Plainsboro Regional School District's passed referendum, the project includes the addition and renovation to West Windsor-Plainsboro High School South. The addition will accommodate a new main office with a secure entrance, classrooms, science labs, robotics room, dance classroom and other spaces. Renovations/Reconfigurations will occur in the following areas: Existing life skills to be reconfigured as culinary sciences lab; existing media center to be reconfigured as learning commons including new finishes, collaboration areas, quick stop area and lounge/gathering spaces; existing robotics room to be renovated; existing main office/guidance suite to reconfigured to a child study team suite and guidance services suite, which will include supports spaces such as conference and work rooms; and renovations to the performing arts playhouse space.

FVHD has been with the district for such a long time (1986), that this is one of many large scale additions and renovations FVHD has worked on for West Windsor-Plainsboro High School South. The most recent was in 2009 CLICK HERE

All of the various project phases are scheduled to be completed at the start of 2022.